Trust The Sun
The Kurnool Ultra Maga Solar Park:
Spread over 5,900 acres between Gani and Sekunala villages off the Kurnool-Nandyal state highway, the solar park is expected to transform the backward region by generating job opportunities for the local youth, besides improving the power supply in the state.
The task of installing over 40 lakh solar panels — about 4,000 for each MW — has been completed in a record time of six months. Over 5, been working on site since November last year. All panels are fixed facing south to north at 13 degrees, for the optimum capture of the power of the sun.
This solar park is bigger than the two comparable projects in the world — Adani Power’s 648-MW plant at Kamuthi in Tamil Nadu and Topaz Solar Farm in California with a capacity of 550 MW.
Land acquisition:
At a time when land acquisition for mega projects is a tricky affair in other states, the farmers of the two villages — Gani and Sekunala—had offered their lands for the park. A major chunk of the 5,900 acres is the government land while over 2, been acquired from private parties under the Land Acquisition Act of 2013 .
Helping hands:
Four private power developers, under the supervision of AP Solar Power Development Corporation Limited, are involved in the execution of the Rs 7,000-crore project. They are: Greenko (500 MW), Japan’s Softbank Energy (350 MW), Azure Power (100 MW) and Prayatna Developers of Adani Group with 50 MW. Over a period of time, the park will produce 2,600 million units of power per annum. The Greenko Group has already started the production.
Funding :
National Thermal Power Corporation had floated the notification-inviting-tender in April 2015 and has, through reverse auction, shortlisted the four developers who quoted a tariff of Rs 4.63 per unit.
While the private developers had invested Rs 6,000 crore, the AP Government contributed Rs 1,000 crore through AP Solar Power Corporation Limited. A sum of Rs 50 crore (Rs 5 lakh per MW) has been collected from the developers for creating social infrastructure and Rs 8 crore has already been disbursed.
The Kurnool park is a major milestone in the journey towards achieving the Centre’s objective of adding 175 Giga Watts (1,00,000 MW of solar, 60,000 MW wind and 15,000 MW of biomass and other such sources) of renewable energy by 2022,” Ajay Jain said.
The target set by the state stands at 10,000 MW of solar and 8,000 MW of wind energy during the period.